Kenyon/Rules/Selling to the city/$25,000 to $175,000
Purchasing tier

$25,000 to $175,000

Two quotes or an RFP; council by resolution

8awards in this band, 2019–2026
$454,211total awarded (where recorded)
$156,445largest
Council, by resolutionwho decides

The rule

State law allows either sealed bids or direct negotiation on two or more quotations, with no advertising required. Kenyon's policy requires two written quotes or an RFP and a council resolution. Engineered work (chip seal, drainage, televising) is run by Bolton & Menk, who email an RFP to contractors they select and tabulate the responses.

Authority: Minn. Stat. 471.345 subd. 4 (sealed bids or direct negotiation on two or more quotations, no advertising); 16C.285 (Responsible Contractor over $50,000); Policy No. 34.

How it runs in Kenyon

  1. For engineered work, Bolton & Menk prepares a short specification and emails it to a list of contractors, or the department head requests quotes directly.
  2. Quotes are tabulated; staff recommends the low responsive quote (or explains why not).
  3. Council adopts a resolution accepting the quote and authorizing the contract.
  4. Contract, insurance certificate and, for construction over $50,000, the Responsible Contractor verification form.
  5. Progress billed through pay applications approved on the consent agenda.

What a vendor sends

  • Get on the engineer's list: Derek Olinger, Bolton & Menk, Rochester, runs every engineered quote; ask to be emailed the next RFP.
  • Quote every alternate; the council usually takes the alternates.
  • Construction over $50,000: sign the Responsible Contractor verification under oath (workers' comp and unemployment compliance, tax registration, no wage violations in three years).

Every award in this band

DateItemProcessAwarded toAmountBidders
2025-05-132025 Bituminous Chip SealrfpPearson Bros (+$20K authority)$59,952Pearson $59,951.55; Asphalt Surface Tech $68,726; Allied Blacktop $69,913.20; Fahrner $96,…
2024-03-12Muni roofquotesstaff rec Chandler Roofing$40,640L&M $53,000 (2022); Chandler $40,640; third attached
2023-12-12Fire Dept SCBA + compressorquotesAlex Air Apparatus$156,445Alex Air Apparatus: SCBA $116,805; compressor $39,640
2022-06-14North Street Drainage OutfallrfpDeCook Drainage$46,018DeCook $46,018.47; Winona Mechanical $51,308.37; Griffin $67,453.60; Fitzgerald $68,808.15…
2022-05-102022 Bituminous Chip SealrfpPearson Bros$44,707Pearson $44,707; Fahrner $58,823
2022-03-08Pearl Creek televising RFP round 1rfpnone1 quote; reissued
2021-08-10FEMA flood repairsrfpGriffin Construction$77,449Griffin low; others unnamed
2021-07-134th St alley pavingquotesCrane Creek Asphalt$29,000Crane Creek $7,727.70 (full ~$29K); Bituminous Materials $9,592.50

From the council record 2019–2026; each item links to its contract page with the proposal documents. Items without a recorded amount are placed by process.